| Scheduling |
|
Preliminary Project Schedule: • Critical dates for pre-construction activities • Critical dates for the issue of plans and specifications • Early bid packages and procurement of long lead-time items • Shop drawings, submittals, fabrication and delivery of long lead items • Schematic and design development estimates • Sub/vendor bidding process • Guaranteed maximum price • Permitting • Start of construction • Construction durations • Substantial completion date • Punch list • Furniture/fixtures/equipment installation by the owner (FF & E) • Final completion date • Certificate of Occupancy date • Owner occupancy date
Design Phase: • Determine lead times and task durations as systems, materials and equipment are selected • Update schedule as new information becomes available
During Construction: • Update overall project schedule weekly • Produce three-week Short Interval Production Schedules (SIPS) • Review schedule for critical delivery and production issues • Distribute and discuss schedule in weekly jobsite meetings with all foremen |